Projects

COMPLETE RENOVATION – Župna Crkva Pohoda BDM Dolac,Zagreb

Project duration: October 2022. – May 2023.

Project details: Demolition and disassembly

  • removal of the central vaults – removal up to the upper part-capital
  • removal of vaults and tension inside the bell tower

Investor: Župa Pohoda Blažene Djevice Marije – Zagreb

Successfully completed the challenging renovation project of the BDM Church in Zagrebački Dolac. Extremely demanding location considering the city center and the narrow approach to the Church. With the use of our highly efficient vacuum truck, hard-to-reach roofs and vaults were successfully treated.

RECONSTRUCTION AND EXTENSION OF THE NEW CROATIAN MUSEUM OF NATURAL HISTORY – Amadeo Palace, Zagreb

Project duration: March 2022. – November 2023.

Project details: Material loading, transportation and disposal of waste material from construction sites and earthworks.

Investor: City of ZAGREB

Performing reconstruction works (demolition, disassembly) of the Natural History Museum of the City of Zagreb.

Demanding execution of a deep excavation along the nearby slope on Tuškanac and subsequent return of the material to the slope.

RECONSTRUCTION AND EXTENSION OF THE NEW CROATIAN MUSEUM OF NATURAL HISTORY – Amadeo Palace, Zagreb

Project duration: March 2022. – November 2023.

Project details: Material loading, transportation and disposal of waste material from construction sites and earthworks.

Investor: City of ZAGREB

Performing reconstruction works (demolition, disassembly) of the Natural History Museum of the City of Zagreb.

Demanding execution of a deep excavation along the nearby slope on Tuškanac and subsequent return of the material to the slope.

URGENT INTERVENTION TO REMEDIAL AN EMERGENCY EVENT on the section of the Meja-Škrljevo railway

Project duration: December 2023.

Project details: Vacuuming of bulk material – corn. Cutting broken wagons. Pulling out freed wagons.

Investor: HŽ Infrastruktura

The emergency intervention of vacuuming loose corn from broken wagons was successfully carried out. In only 4 days, the emergency intervention team removed the broken wagons and cleared the corridor for the continuation of rail traffic on the Rijeka-Zagreb route.

URGENT INTERVENTION TO REMEDIAL AN EMERGENCY EVENT on the section of the Meja-Škrljevo railway

Project duration: December 2023.

Project details: Vacuuming of bulk material – corn. Cutting broken wagons. Pulling out freed wagons.

Investor: HŽ Infrastruktura

The emergency intervention of vacuuming loose corn from broken wagons was successfully carried out. In only 4 days, the emergency intervention team removed the broken wagons and cleared the corridor for the continuation of rail traffic on the Rijeka-Zagreb route.

RECONSTRUCTION OF THE SUGAR PALACE – Rikard Benčić Complex, Rijeka

Project duration: April 2018. – August 2019.

Project details: Disassembly and demolition.

Investor: City of RIJEKA

Performing reconstruction works (demolition, disassembly) of the Šećerana Palace within the complex Rikard Benčić in Rijeka.

RECONSTRUCTION OF THE SUGAR PALACE – Rikard Benčić Complex, Rijeka

Project duration: April 2018. – August 2019.

Project details: Disassembly and demolition.

Investor: City of RIJEKA

Performing reconstruction works (demolition, disassembly) of the Šećerana Palace within the complex Rikard Benčić in Rijeka.

ADAPTATION OF A FAMILY HOUSE

Project duration: February 2024.

Project details: Disassembly of woodwork, wall and floor coverings. Demolition of partition walls, ceiling. Plastering. Chimney disassembly. Floor lowering. Total area 90m2.

Investor: Private investor

All activities were performed in a record time of 12 working hours!

RECONSTRUCTION OF A RESIDENTIAL AND BUSINESS BUILDING – Bakačeva 3, Zagreb

Project duration: September 2021. – November 2022.

Project details: Demolition, disassembly, earthwork.

Investor: Strabag d.o.o.

An extremely challenging project considering the demolition of the building between two existing buildings on both sides.

A demanding location in the center of Zagreb – Ban Jelačića Square

Work done all manually, without machines.

RECONSTRUCTION OF A RESIDENTIAL AND BUSINESS BUILDING – Bakačeva 3, Zagreb

Project duration: September 2021. – November 2022.

Project details: Demolition, disassembly, earthwork.

Investor: Strabag d.o.o.

An extremely challenging project considering the demolition of the building between two existing buildings on both sides.

A demanding location in the center of Zagreb – Ban Jelačića Square

Work done all manually, without machines.

REMOVAL OF SILOS for the preparation and storage of well cements and barite in Ivanić – Grad

Project duration: January 2024. – March 2024.

Project details: Demolition and removal of silos

Investor: CROSCO naftni servisi d.o.o., Zagreb

Disassembly and removal of processing, material loading and receiving silos together with the associated concrete base, removal of work equipment from the compressor station and control unit, dismantling of the road scale and removal and cleaning of all waste material for the conversion of space and premises for the needs of the company Crosco d.o.o.

DEMOLITION OF THE CHIMNEY of ŠSD Peščenica

Project duration: September 2022. – December 2022.

Project details: Demolition of the brick chimney.

Investor: City of Zagreb, Management of sports facilities

A demanding task of removing the chimney, given the proximity of the surrounding buildings and the height of the chimney itself.

DEMOLITION OF THE CHIMNEY of ŠSD Peščenica

Project duration: September 2022. – December 2022.

Project details: Demolition of the brick chimney.

Investor: City of Zagreb, Management of sports facilities

A demanding task of removing the chimney, given the proximity of the surrounding buildings and the height of the chimney itself.

RENOVATION AND REVITALIZATION PROJECT OF ERDODY CASTLE – Jastrebarsko

Project duration: January 2024. – April 2024.

Project details: Demolition, disassembly and removal.

Investor: City of Jastrebarsko

Construction project of complete renovation and revitalization of cultural heritage – Erdody Castle in Jastrebarsko.

COMPLETE RENOVATION OF THE CONSTRUCTION of the College of the Society of Jesus – Jordanovac, Zagreb

Project duration: February 2022. – February 2023.

Project details: Demolition, disassembly and earthworks.

Investor: Society of Jesus college – Jordanovac, Zagreb

Construction project, complete renovation of the structure.

Exceptional volume of work done – complete disassembly and demolition of all internal elements, except external walls.

COMPLETE RENOVATION OF THE CONSTRUCTION of the College of the Society of Jesus – Jordanovac, Zagreb

Project duration: February 2022. – February 2023.

Project details: Demolition, disassembly and earthworks.

Investor: Society of Jesus college – Jordanovac, Zagreb

Construction project, complete renovation of the structure.

Exceptional volume of work done – complete disassembly and demolition of all internal elements, except external walls.

RENOVATION AND RENOVATION PROJECT OF THE BUILDING OF THE ARCHBISHOP’S PALACE – Kaptol, Zagreb

Project duration: September 2022. – July 2023.

Project details: Demolition and disassembly.

Investor: Archdiocese of Zagreb – Nadbiskupski Dvor, Kaptol Zagreb

Construction project of complete renovation of the structure.

DEMOLITION of the business building Spar – Grubišno polje

Project duration: December 2023.

Project details: Disassembly and demolition of the entire Spar Shopping Center

Investor: SPAR

Disassembly and demolition of the entire Spar Shopping Center including the concrete slab, Grubišno polje.

DEMOLITION of the business building Spar – Grubišno polje

Project duration: December 2023.

Project details: Disassembly and demolition of the entire Spar Shopping Center

Investor: SPAR

Disassembly and demolition of the entire Spar Shopping Center including the concrete slab, Grubišno polje.

RECONSTRUCTION OF THE T-BUILDING ex Benčić complex into the Rijeka City Library

Project duration: October 2019. – July 2021.

Project details: Construction project of supporting the existing structure

Investor: City of Rijeka

Disassembly and demolition of all floors inside the external walls and supporting the external facade walls with heavy scaffolding.